Council issue update on Tyne Bridge work as new scaffolding process begins

New scaffolding is being erected around the Tyne Bridge, signalling the next phase of its restoration.

With the latest phase of work on the main bridge deck now complete, the next phase will see scaffolding, termed as 'up and overs', installed from the underdeck, up the side and over the bridge parapet onto the footway

This is done to enable repairs and repainting works to be carried out on the screen plate and the parapets.

New scaffolding is being erected around the Tyne Bridge's parapet (Image credit: Esh Construction)placeholder image
New scaffolding is being erected around the Tyne Bridge's parapet (Image credit: Esh Construction) | Esh Construction

As part of this phase, a pedestrian tunnel will be constructed on each footway so people can use the bridge as work progresses.

Cllr Juna Sathian, Newcastle City Council’s cabinet member for transport and climate said: "It's great to see such fantastic progress being made on the Tyne Bridge, as we restore an icon to its former glory.

“With all eyes on the Tyne Bridge as part of another successful Great North Run, where the need for the repairs was visible for all to see, it's great that work will soon move onto this key part of the structure.

"As we've set out before, it's a complicated programme with 20 different phases of scaffolding required, which has been meticulously calculated due to the weight loading, as well as ensuring the bridge remains open for traffic and pedestrians over the four-year programme."

How long will the Tyne Bridge work take?

The council has confirmed the temporary pedestrian tunnel will be in place from “early 2026” with another tunnel expected on the east footway at a later date.

This is part of a four year programme expected to be complete by the summer of 2028, in time for the 100 year anniversary of the bridge opening in October 2028.