Latest update on Newcastle’s Outer West Leisure Centre – more major setbacks sink pool dream


Building work is still yet to begin on a Newcastle leisure centre that was meant to open a year ago.
It was originally hoped that the new Outer West Leisure Centre in West Denton would be ready to open its doors in the summer of 2024.
But the long-awaited sports complex continues to suffer repeated setbacks and bosses now say it is unlikely to be completed until late 2027.


Construction work on the £34 million facility, which is earmarked for the site of the demolished Outer West Pool and library in West Denton Way, has not even started yet.
Newcastle City Council, which previously predicted this April that building would begin this summer, blamed the presence of a high-voltage cable which needs to be diverted away from the site for the latest delays.
Final agreements with a construction firm are also yet to be signed, while the local authority has already switched contractors once in order to rein in the spiralling costs of the project.
Locals have been left without a swimming pool in their community since the old Outer West Pool was shut at the start of the Covid pandemic in 2020 by operator GLL and, controversially, was never reopened.
Newcastle City Council won £19.8 million of Government funding to help pay for a state-of-the-art replacement, originally expected to cost a total £22.3 million, in 2021.
The new complex should eventually be able to boast a 25m swimming pool with eight lanes, a 17m training pool, an aqua play pool, a sports hall, a fitness studio and gym, a library, community spaces, a soft play area, and a café.
Essential work to fill in old mine workings beneath the site has been completed, but there remain other problems holding back the scheme.
A council spokesperson insisted this week that the local authority “remains fully committed” to opening the new leisure centre.
They added: “Progress is continuing with the enabling works, however the next phase is dependent on Northern Power Grid diverting a high-voltage cable that currently runs across the site. This essential work will allow for the realignment of the access road to the shopping centre.
“For safety reasons, the subway under West Denton Way, which connects to this part of the site, has been temporarily closed. We apologise for any inconvenience this may cause and thank residents for their patience. An alternative walking route is in place for the duration of the works.
“Regarding the main leisure centre scheme, the building’s external design has been updated and is expected to receive planning approval in the next few days. Commercial negotiations with the main contractor are ongoing and we will provide a further update once agreements are finalised.
“Construction of the pool building is anticipated to begin once enabling works are complete, with the centre scheduled for completion later in 2027.
“We appreciate the community’s continued support and will keep residents informed as the project progresses.”