Northumberland Line connecting the county to Newcastle to open from Summer 2024

Watch more of our videos on ShotsTV.com 
and on Freeview 262 or Freely 565
Visit Shots! now
The first three stations of the Northumberland Line are set to open this summer.

The Northumberland line- bringing passenger services back between the South East of the county and central Newcastle- will be open from Summer 2024.

Hide Ad
Hide Ad

To allow services to start at the earliest opportunity, there will be a phased approach to the service- with Ashington, Newsham and Seaton Delaval opening this summer.

With a journey time between Ashington and central Newcastle of around 35 minutes, the line will improve accessibility to employment, training and leisure.

Newsham, BlythNewsham, Blyth
Newsham, Blyth | Northumberland County Council

There is no date for the opening of the Northumberland Park, Blyth Bebside or Bedlington stations yet.

Hide Ad
Hide Ad

Council Leader Glen Sanderson said: “We’re delighted to confirm passenger trains will be running from Summer 2024 and this will be an absolute game changer for transport in the area.

“The line will bring so many benefits in terms of work and education opportunities, inward investment and business growth in the county and a reduction in congestion.

“We understand there may be some disappointment by adopting this phased approach and thank people for their patience while this critical work continues.

Hide Ad
Hide Ad

“Every single person involved with the Northumberland Line is working hard to deliver this fantastic scheme – but a lot of hard work still lies ahead.

“This is a hugely complex project with major station construction works being undertaken at six separate sites, signalling and track improvements along the line and changes to numerous level crossing points all of which must be co-ordinated and undertaken to minimise disruption to local communities, rail freight services and road users.

“As with any project under construction, challenges and issues have arisen, but we can’t let that overshadow the fact that the service will be up and running this year or the benefits that will bring.

Hide Ad
Hide Ad

“At the same time it’s crucial we get the Northumberland Line open and allow people to start making use of the line as soon as possible.”

There are a variety of issues that have arisen which mean it is not possible to open all six stations this summer.

The most common causes at the remaining stations are adverse ground conditions – including contamination and buried services, inflationary pressures and historic mine workings. There are also complex interfaces with signalling and access to the railway which remains open to freight trains.